New Critical Access Hospital & Skilled Nursing Facility - Contingency Usage Request 009

Requesting Board approval for Contingency Usage Req #33, Generators upsize, for an added cost of $79,173.46; Req #34, Electrical scope changes on INCs 1 & 2, for an added cost of $297,323.52; and Req #35, Envelope revisions, for an added cost of $260,854.88.#33 and #34 are necessary due to electrical design refinements made by the current electrical engineer of record (replacing the EEOR at the time of bid).#35 incorporates input from the commissioning consultant upon review of the envelope, to improve waterproofing and flashing installations.Together with the items separately approved per SHD BOD Resolution #452 and documented in the Board packet, once #33, #34 and #35 are approved, Owner's Contingency remains at $757,780.92 and Construction Contingency remains at $4,652,623.86. Presented by Donna Huntingdale, Building Rx. 

Your Info (Be advised all personal information you enter below will be displayed. All fields are optional.)

Name
City
Zip
Phone
Email

Your Comment