Public Comment
Informing of Contingency Usage Request #43, additional mock-up testing, for an added cost of $16,500.00.These items have been separately approved per SHD BOD Resolution #452 and documented in the Board packet. With #43 approved, Owner's Contingency remains at $1,158,760.92 and Construction Contingency remains at $4,633,734.49. (attached CUR011 memo, Capital Engineering ASR1 & ASR2)Report presented by Donna Huntingdale, Building Rx.