New Critical Access Hospital & Skilled Nursing Facility - Contingency Usage Request 012

Contingency Usage Requests #44, Foundation Waterproofing, for an added cost of $53,957.20; #45, Updating GC contracted scope on INC3 from bid to permit drawings, for an added cost of $382,942.17; #46 & #47, Mock-up retest #3 costs being shifted from Owner's Contingency to be paid by GC, for a shift of costs of $8,250.00; #48, Transition and Activation Planning contract budget supplementation, for an added cost of $112,154.00; #49, Medical Gas Inspection/Certification, for an added cost of $116,905.33; and #50, Lab Grant, for a reduced Contingency Usage of $398,781.41.Once items 44-50 are approved, Owner's Contingency remains at $1,336,733.33 and Construction Contingency remains at $4,203,100.77. Presented by Donna Huntingdale, Building Rx